Gaps in the inverter manufacturer’s digital twin caused the model to consistently fail PSCAD stability studies.

Hyde Renewables coordinated a series of revisions and studies to prove HECO stability conditions were met by the inverter. PSCAD model delivery and site tuning is a standard milestone for the interconnection process with HRE.